- The material handling system meets defined needs, but requires ongoing control and communication.
- A ~38% cut in planned number of miners achievable, while still meeting required plant throughput (>USD10 million capital investment saving.)
- Planned capacity of certain conveyors exceed base case tonnage needs and related capital investment could be mitigated.
- Planned capacity of storage adequate to handle expected needs, though limits periodically tested.
Material Handling Simulation